Deciding When to Redefine Your Project

As you make changes to your schedule, you might want to consider rescheduling remaining work to start as of a particular date so that you can get things back on track in your schedule. You can quickly and easily reschedule any remaining work for partially completed or uncompleted tasks using the Update Project dialog box (see 12-8). Start by displaying any task-oriented view. If you plan to update only selected tasks, select them by clicking their ID numbers. Then on the Tools menu, point to Tracking, and click Update Project.

You can quickly and easily reschedule uncompleted work.

Figure 12-8. You can quickly and easily reschedule uncompleted work.

The Reschedule ...