CONTROL PROCESS67Project Variance Analysis (PMBOK® 4.4, Monitor and Control Project Work)

What:

Identifying differences between baseline plans and actual performance.

When:

Project execution and control.

Results:

Prompt recognition of problems and issues.

Verify Status

Project variance analysis is central to project plan execution. It follows status collection in the project-tracking cycle. Before beginning to analyze variance, validate the status information. Check it for completeness, consistency with past data, and credibility compared with other current status and project information.

Determine Variances

Compare the status reported with your commitments from project baseline setting. Note all differences, both beneficial and adverse. ...