The WBS and the Network Diagram

A WBS is a great first step in identifying the work packages in a project. However, WBS representations don’t graphically display the sequencing relationships between various parts of the project. A WBS shows only the hierarchical relationships between work on the project; you can’t schedule a hierarchy as easily as a sequence. Therefore, you cannot use it to create a schedule or to coordinate work done by different people or resources unless all the activities in a project are sequential, which they rarely are.
Complex Gantt charts can display relationships among the activities, and these are best produced by computer programs. (See Chapter 11 for more on Gantt charts.) Network diagrams are an easier way to ...