Improving Your Outlook

Now that you know how to create, assign, and track your tasks, we'll look at a complicated business project made easier through the use of tasks. The project you're responsible for is a network infrastructure upgrade project. On a Friday afternoon, you receive the email shown in Figure 14.26.

Figure 14.26. You have 30 days to complete a network infrastructure upgrade.

After you get over your initial panic, you start to plan. You need to make a listing of all the various actions you need to take to complete this project:

  • Inventory current servers— List software installed, current hardware specifications, server name, and ...