CHAPTER16

ImplementingCorrective Actionsand Executingthe Plan

Talk doesn’t cook rice.

—Chinese Proverb

If the result of the negotiation is to continue the project, it needs to be reset to the definition phase. It now has a scope of work, tentative timeline, potential resource list, initial risk register, and project assumptions; it is ready to roll. It has the traits of a new project, and everyone should treat it as such.

Implementing Corrective Actions

Before restarting the project, implement the corrective actions. Treat their implementation as any other project’s prerequisite start-up tasks. Shuffle the team, acquire new people, and make new assignments. The scope was probably altered, and the plan now has different objectives. As opposed ...