- The following table lists the activities of a maintenance project:
Activity Duration (in months) 1-2 2 1-3 2 1-4 1 2-5 4 3-6 5 3-7 8 4-7 3 5-8 1 6-8 4 7-9 5 8-9 3 - Draw the project network.
- Find the critical path and duration of the project.
- Suppose we are required to employ a special piece of equipment on activities 1-3, 3-6, 2-5, 5-8 and 8-9, one at a time. Will it affect the duration of the project? Explain.
[Ans: CP: 1-3-7-9 with 15 Days, Unaffected]
- A project with normal duration and cost alongwith crash duration and cost for each activity is given below:
The ...