ASSUMPTIONS OF CPM/PERT
- A project can be sub-divided into a set of predicable, independent activities.
- The precedence relationships of project activities can be completely represented by a non-cyclical network graph in which each activity connects directly into its immediate successors.
- Activity times may be estimated either as single point estimates or as three point estimates (i.e. optimistic, pessimistic or most likely) and are independent of each other.
- Activity duration is assured to follow the beta distribution, the standard deviation of the distribution is assumed to be 1/6th of its range.Mean (te) is assumed to be = .Variances in the length ...