PRACTICAL QUESTIONS
- Draw a network from the following activities and find critical path and duration of project.
[Ans: CP: 1 - 3 - 7 - 10 - 12 - 13 with 28 days]
- Draw a network from the following activities and find a critical path and total duration of project.
[Ans: CP: 1 - 2 - 4 - 5 - 6 - 7 with 35 days]
- Draw a network from the following activity and find critical path and duration of project.
[Ans: CP: 1 - 2 - 6 - 7 - 8 - 9 with 16 days] ...