LATEST START TIME (LST)

The latest start time of an activity is equal to the latest finish time of the activity minus the duration of that activity.

Example –

The computation of EFT and LST is shown below:

The computation of EFT and LST

Get Quantitative Techniques: Theory and Problems now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.