HOW TO COMPUTE EARLIEST START TIME FOR EACH NODE (E)
The steps involved in the computation of Earliest Start Time for each node (E) are as follows:
Step 1→ | Identify all the activities leading to each node. |
Step 2→ | Calculate the sum of expected Time of each set of activities leading to each node. |
Step 3→ | Calculate the maximum of the sum of expected time of each set of activities (as per step 2). |
The aforesaid calculations may be presented in the form of following table:
Table Showing the Computation of Earliest Start Time (E)