237. Answer: B.

PMBOK® Guide, Glossary; and page 345, Section 11.5.2.1

Acceptance Criteria. A set of conditions that is required to be met before deliverables are accepted.

Performance Measurement Baseline. An approved, integrated scope-schedule-cost plan for the project work against which project execution is compared to measure and manage performance. The PMB includes contingency reserve, but excludes management reserve.

Accept.…This strategy can be either passive or active. Passive acceptance requires no action except to document the strategy, leaving the project team to deal with the risks as they occur, and to periodically review the threat to ensure that it does not change significantly. The most common active acceptance strategy ...