Stakeholder Management

(Chapter 13 of the PMBOK ® Guide)

217.  Stakeholders are:

A. The project engineers who design and construct the project.

B. The people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project.

C. The organization's corporate attorneys.

D. The individuals or agencies that control contingency funds and their disbursement through the project management office (PMO).

218.  Which of the following is NOT true about project stakeholders?

A. They are people, groups, or organizations that are actively supportive of the project.

B. They are people, groups, or organizations who are involved in the project.

C. They people, groups, or organizations whose interests may be positively ...