161.  The major processes of Project Communications Management are:

A.  Plan Communications Management, Manage Communications, and Control Communications.

B.  Plan Communications Management, Develop Responses, Report Progress, and Distribute Information.

C.  Plan Communications, Distribute Information, and Schedule Reporting.

D.  Distribute Information, Report Changes, Update Project Documents, and Accept Project Deliverables.

162.  Inputs to the Plan Communications Management process include:

A. Project management plan, stakeholder register, enterprise environmental factors, and organizational process assets.

B. Stakeholder requirements, project scope statement, project budget, ...