Sample questions
1 |
1. Which of the following is not a name given to the group which has responsibility for committing resources to the project and approving variations to the project’s objectives?
(a) project board; (b) project management board; (c) project support office; (d) steering committee. |
2 |
2. Which of the following terms is used to describe an organizational structure where staff are responsible to a project manager for the duration of a project but also have a manager who is responsible for their long-term staff development and work programme?
(a) the Tuckman model; (b) configuration management; (c) matrix management; (d) task orientation/relationship orientation. |
3 | 3. At which stage of team formation does a team become fully ... |