Sample questions
1 |
1. An under-estimate of effort is MOST likely to lead to which of the following?
(a) decreased productivity; (b) decreased quality; (c) a less competitive bid for a contract; (d) a longer project duration. |
2 |
2. Which of the following estimating methods is MOST likely to be used bottom-up?
(a) parametric; (b) algorithmic; (c) Delphi; (d) activity-based. |
XYZ organization ScenarioStaff have managed to develop information systems at a rate of five function points per staff-day. A new system has been assessed as requiring 120 function points to implement, but the staff available are relatively inexperienced and are only 80% as productive as the staff usually used in such projects. |
Both questions 3 and 4 use this scenario ...