Pointers for activities

Activity 3.1

Activity 3.1
  1. If we keep to the original planned training delivery rate of one boatyard a day, 17 days (that is, about three to four weeks) are needed to complete training, as there are 17 boatyards left. However, if we decide that the experience of the first week shows that the original delivery rate was unrealistic, then we may project that three boatyards can be visited in a week. This would lead to between five and six weeks being needed to complete training.

    1. In this scenario, the reason for only three boatyards being visited was simply a late start rather than a low delivery rate. The estimate of 17 days ...