Sample questions
1 |
1. Which of the following is NOT a characteristic of a project?
(a) Ongoing nature (b) Uniqueness (c) Clear objectives (d) Integration of interrelated tasks and resources |
2 |
2. Which of the following is NOT managed by the project manager?
(a) Time, cost and scope (b) The project team (c) The project sponsor (d) Expectations of the stakeholders |
3 |
3. Which of the following tools indicates who is responsible for what?
(a) A responsibility assignment matrix (b) A resource levelling chart (c) An activity network chart (d) A resource histogram |
4 |
4. With which one of the following does the calculation of the payback period provide the organization?
(a) An assessment of how quickly an implemented system will produce a profit. ... |