1 1. Which of the following is NOT a characteristic of a project?

(a) Ongoing nature

(b) Uniqueness

(c) Clear objectives

(d) Integration of interrelated tasks and resources

2 2. Which of the following is NOT managed by the project manager?

(a) Time, cost and scope

(b) The project team

(c) The project sponsor

(d) Expectations of the stakeholders

3 3. Which of the following tools indicates who is responsible for what?

(a) A responsibility assignment matrix

(b) A resource levelling chart

(c) An activity network chart

(d) A resource histogram

4 4. With which one of the following does the calculation of the payback period provide the organization?

(a) An assessment of how quickly an implemented system will produce a profit. ...