CHAPTER 4

SCHEDULING COMPONENTS

The following section provides a detailed cataloging of the potential components of a scheduling tool. Each entry includes eight possible types of information related to each component, and indicates whether the component is considered to be required, conditional, or optional by this practice standard. Required components are divided into four groups: Core Required Components (CRC, shown as “R” in the tables), Resource Required Components (RRC), EVM Required Components (ERC) and Risk Required Components (KRC). The requirements of the project determine which required components need to be present in a schedule model before a maturity assessment can be performed. The maturity assessment and conformance index are ...