Appendix L

Telecom WBS Example

The WBS example below is displayed in a standard outline format. At level 2, this WBS is organized according to the project lifecycle, from creation of the concept through product development, customer acceptance and ongoing support and maintenance. Within each level 2 WBS Element are included lower level deliverables that are specific to that stage and include, among others, reviews and decisions, analyses, tangible deliverables, and services. The Project Management WBS Element is not decomposed to the same level of detail as the others. Both an outline and vertical tree-structure view are provided for comparison.

1 WBS for Telecom Project

1.1 Concept/Feasibility

1.1.1 Concept

1.1.2 Marketing Analysis

1.1.3 ...