FIRST-CUT PROJECT PLAN

A plan should be developed that shows the interdependencies of the deliverables within this work stream. Have a look at the control points in the following chapters and see how they match with your use of the tools in your strategy.

A plan should be developed that links the stages outlined in your data migration strategy to the deliverables coming out of the rest of the programme. This will protect you if (when?) there is slippage elsewhere in the programme.

Your plan will be very high level at the moment. You do not know the number or complexity of Data Quality Rules documents you will be creating for instance. It should be an indicative plan for Stage 1 Data Preparation based on the project brief you have been given ...