QUESTIONS FROM PREVIOUS QUESTION PAPERS
  1. Derive the coordination equation for the optimal scheduling of hydrothermal interconnected power plants.

     

  2. Explain long range hydroscheduling. Derive necessary expression.

     

  3. Discuss the cost associated with hydroplants.

     

  4. State what is meant by base load and peack load stations. Discuss the combined bydroeletric and steam station operation.

     

  5. Explain the problem of scheduling hydrothermal power plants. What are the constraints is the problem?