Chapter 12. Answers to Practice Exam 2

1.

Answer D is correct. The project charter formally authorizes the project, assigns the project manager, and gives a high-level definition of the projects and its deliverables; none of the other answers apply to the project chapter definition.

2.

Answer B is correct because projects are seeded from the recognition of a regulatory or business need. However, when it comes to measuring the actual organizational benefit, your client or company needs to make arrangements to secure the capital and reserve assignments. For this type of allocation, the aforementioned models are just a few of the tools at your disposal to find a measure of the enterprise benefit and the cost justification. You could have selected answer ...