Chapter 1

Quiz 1

1. You are a project manager working for a large utility company. You have been assigned the responsibility to manage a project that performs monthly security vulnerability assessments and addresses any identified vulnerabilities. You question the assignment because

Image A. Security vulnerability assessments do not materially contribute to your organization’s products and should not be considered important enough to be classified as a project.

Image B. This endeavor cannot be considered a project ...