Section 10

Project Stakeholder Management

1 QUESTION

Define a stakeholder.

ANSWER

An individual, group, or organization that may be affected by or perceive itself to be affected by a decision, activity, or outcome of a project.

[Initiating and Planning]

2 QUESTION

List the four processes in Project Stakeholder Management.

ANSWER

  • Identify stakeholders
  • Plan stakeholder management
  • Manage stakeholder engagement
  • Control stakeholder engagement

[Initiating, Planning, Executing, and Monitoring and Controlling]

3 QUESTION

What is the benefit of plan stakeholder management?

ANSWER

It provides a clear, actionable path to interact with project stakeholders to support the interests of the project.

[Planning]

4 QUESTION

List three tools and techniques in ...