APPENDIX 2 – PCI DSS PROJECT PLAN
Steps |
Description |
Duration |
Start |
Finish |
Step 1 |
||||
|
Establish PCI project |
2 days |
03/03/08 |
04/03/08 |
|
Agree objectives and sponsor |
1 day |
05/03/08 |
05/03/08 |
|
Agree escalation/communication |
1 day |
06/03/08 |
06/03/08 |
|
Create PID |
2 days |
07/03/08 |
10/03/08 |
|
Sign off on PID |
0 days |
10/03/08 |
10/03/08 |
|
Create draft SIP |
2 days |
11/03/08 |
12/03/08 |
Step 2 |
||||
|
Determine the scope |
1 day |
13/03/08 |
13/03/08 |
|
Scope workshop |
1 day |
14/03/08 |
14/03/08 |
|
Document scope |
2 days |
17/03/08 |
18/03/08 |
|
Sign off on scope |
0 days |
18/03/08 |
18/03/08 |
Step 3 |
||||
|
Review IS policy |
2 days |
19/03/08 |
20/03/08 |
|
Review set of supporting policies |
2 days |
21/03/08 |
24/03/08 |
|
Conduct policy analysis |
2 days |
25/03/08 |
26/03/08 |
|
Make ... |