Practising With Some Questions
On the following pages you’ll find some questions based on the Controlling a Stage process. You’ll find the answers, with a bit of explanation, on the grey-edged pages at the end of the chapter.
Foundation-level questions
Have a go with these questions to check your knowledge at Foundation level. Try to do the questions in eight minutes or less.
1. What’s the name of the progress report produced by the Project Manager in the process Controlling a Stage?
a) Stage Progress Report
b) Highlight Report
c) Checkpoint Report
d) Stage Control Report
2.