Resource curves

When resources perform work on an activity, you can choose how the resource units or costs are spread through time. This is done using a resource curve. To see this column, right-click on the Resources tab on an activity, customize the columns, and choose Curve.

Resource curves

A wealth of curves from which to choose is presented. These curves will determine how the effort and cost of a resource is spread over time. This could reflect expected cost for labor or the expected consumption of a material resource.

To view and modify resource curves, choose the menu Enterprise | Resource Curves. A list of resource curves, much like the one shown in the ...