Formula Review

  1. Calculating the projected available quantity:

    Projected available = beginning inventory + MPS shipment

    – forecasted demand

  2. Calculating a planning factor for direct labor:

    Planning factor for direct labor

    images

  3. Calculating a planning factor for machine time:

    Planning factor for machine time

    images

  4. Calculating projected available quantity when using ATP MPS records:

    Projected available = beginning inventory + MPS shipment

    – the greater of the period's forecast or the actual customer orders promised for delivery that period

  5. Calculating ATP quantity in the action bucket:

    ATPAction Bucket = beginning inventory + MPS shipment

    – customer orders before next replenishment

  6. Calculating ATP quantity at future replenishment periods: ATP = MPS shipment

    ATP = MPS shipment

    – customer orders between current MPS shipment and next scheduled replenishment