Appendix D: Sample Project Work Plan

Task

Duration

Start Date

End Date

Certify ABC System

52 days

10-Nov-13

9-Jan-14

Project preparation

2 days

10-Nov-13

11-Nov-13

Coordinate project with system owner

1 day

10-Nov-13

10-Nov-13

Obtain system inventory information

2 days

10-Nov-13

11-Nov-13

Set up project directory

1 day

10-Nov-13

10-Nov-13

Develop project plan

0 days

11-Nov-13

11-Nov-13

Project kickoff

5 days

11-Nov-13

17-Nov-13

Schedule kickoff briefing

2 days

11-Nov-13

12-Nov-13

Prepare kickoff briefing

1 day

12-Nov-13

12-Nov-13

Present kickoff briefing

1 day

17-Nov-13

17-Nov-13

Update project plan

0 days