Planned versus committed projects

Before we end the chapter, let's quickly discuss the difference between planned and committed projects. The major difference between planned and committed projects is that committed projects affect the time remaining, assuming that this policy option is enabled as per the recommendation in this chapter. The difference between the two project types also allows an administrator to see, at a glance, what projects are definitely going to occur vs. what projects are in the maybe category.

Planned projects are useful for analyzing the impact of future projects or changes in your environment that have not yet been confirmed. They are also useful for modeling different scenarios, such as changes to supply. It is ...