Chapter 7: 4D Sequencing with TimeLiner
Link your model to a project schedule.
Navisworks links to common scheduling applications as a means to add schedule data to TimeLiner.
Master It
What formats don't require an installed scheduling application to view their data?
Solution
Both MPX and CSV files can be accessed without a separately installed scheduling application.
Create a 4D sequence.
Navisworks creates 4D models by linking in schedule data to generate models that address the time and spatial aspects of a construction site.
Master It
What is the benefit of using a 4D model compared to traditional coordination efforts?
Solution
4D modeling allows for a better understanding of the project schedule by removing the limitations of traditional ...