Timeline

The goal of the project was to make the PUST system available to all police in Sweden by early 2011. Development started around September 2009. The first release to production (a pilot) happened one year later, followed by a series of bimonthly follow-up releases.

images/About-the-project/Timeline.png

The project size was initially about ten people in Q3 2009, scaled to about thirty people in mid-2010, and then doubled to sixty-plus people in Q4 2010.

The key milestones were 1.0 (the first pilot release to real users) and 1.4 (the nationwide release). The system will, of course, continue to evolve over many years, so 1.4 is by no means the last release.

One year to ...