Managing server failures

I have prepared an environment to test the pool pairing failover and failback based on two different sites (Site 1 and Site 2) and a Standard Edition server in each site, as shown in the following diagram:

Managing server failures
  1. The first step is to modify the topology using the Topology Builder. We have to select one of the Standard Edition servers and select Edit Properties.
    Managing server failures
  2. The modifications we have to perform in the Front End properties (as shown in the following screenshot) are as follows:
    1. Modify the Resiliency parameter.
    2. Check Associated backup ...