Chapter 7. Producing a Workable Schedule

Once a suitable network has been drawn, with durations assigned to all activities, it is necessary to determine where the longest path is in the network and to see whether it will meet the target completion date. Since the longest path through the project determines minimum project duration, any activity on that path that takes longer than planned will cause the end date to slip accordingly, so that path is called the critical path.

Get Fundamentals of Project Management, Third Edition now with the O’Reilly learning platform.

O’Reilly members experience books, live events, courses curated by job role, and more from O’Reilly and nearly 200 top publishers.