Discussion Questions

1.How would you go about the task of decomposing the project into meaningful business chunks? Speak to the rules you might employ.
2.You have completed the first few increments and released deliverables to the customer. The customer is now coming to you with changes to what has been released. These changes make sense but will cause your project to go off schedule if integrated into the future increments. What would you do?