Chapter 8.2.2. Flow control

Page 153

Chapter 8. Work Management 153 Figure 8- 11 Example of a work type to start process flow control when work order status is in progress 8.2.2 Flow control Flow control enables a task sequence to be executed automatically. Task flow sequences are used to indicate the steps necessary to complete a work order following a structured plan. The Predecessors field, located in each task, is used to define the task predecessors that enable tasks to start in a planned sequence. This field determines all predecessor tasks that have to end their flow before starting the flow of the next tasks. A task flow control is controlled by the Under Flow Control check box, which enables the task to change its status considering the ...