RECOVERY

If you are at this point and recovery is necessary, it is clear the System Test was not created concurrent with the system. You are probably the recovery project manager because the one that got the project to this point is somewhere else!

There are four steps that must be taken:

First, a lot of documentation must be reviewed. The original requirement and all changes to the baseline must be reviewed. The baseline must be updated (or, if you are really in trouble, created) to reflect the last documented baseline of the system. The baseline would now be established, but it must be validated. This is the tricky part. The only way to validate the current requirements baseline is to negotiate it with your customer. From the customer's standpoint, ...