RECOVERY
Start back with the Specification and develop a Requirements Traceability Matrix (see Attachment 7) similar to Table 4-6 below. Add a column for the monitor's name.
Cover every requirement, assign monitoring responsibility for every requirement, and establish a schedule for frequent reporting from the monitor to the project leadership.
SOW/Spec Para | Requirement | WBS Number | S/C SOW/ Spec Para | Unit Test Number | System Test Para | Monitor |
---|---|---|---|---|---|---|
SOW | ||||||
4.3.1 | Security | 06-03-02 | N/A | T-0304 | 4.4.1 | Smith |
Spec | ||||||
3.2.1 | System weight shall be less than 10,000 pounds | 02-04-03 | 3.4.6 | T-0045 | 3.4.1 | Jones |
2f (NO) The Specification is not being properly performed
The Specification is not being properly performed when ...